On November 1, the Federal Energy Regulatory Commission rejected an amended interconnection agreement filed by PJM Interconnection for the ...
Chairman Willie Phillips dissented from the decision on the “first of its kind” co-location proposal, saying it could harm ...
The commission agreed with opponents of the proposal, citing concerns about grid reliability and cost fairness.
FERC rejected an interconnection service plan proposed to raise the load capacity of an Amazon data centre at Susquehanna ...
The company’s “foot is on the accelerator” to close data center deals as it works to restart Three Mile Island Unit 1 by 2027 ...
The US Federal Energy Regulatory Commission (FERC) has issued an order rejecting the amended Susquehanna Interconnection ...
The Federal Energy Regulatory Commission (FERC) denied an amended Interconnection Service Agreement (ISA) that would have ...
The US Federal Energy Regulatory Commission (FERC) has rejected a proposal that would have allowed an Amazon data centre ...
The Federal Energy Regulatory Commission (FERC) rejected the ISA last week. The proposal aimed to revise an ISA involving PJM, the regional grid operator Susquehanna Nuclear, which owns the power ...
Morgan Stanley notes that on Friday, the Federal Energy Regulatory Commission, or FERC, rejected the proposed Interconnection Service ...
Jefferies notes that the Federal Energy Regulatory Commission, or FERC, issued an order rejecting the amended Interconnection Service Agreement, or ISA, between Susquehanna Nuclear, a Talen Energy ...
The proposal aimed to revise an ISA involving PJM, the regional grid operator, Susquehanna Nuclear, which owns the power plant, and transmission owner PPL Corp. The amendment would boost the data ...